Avaza#
Adding a new Resource to the Project#
Pre-Requisites
- Must be assigned as a Project Manager for the project in Avaza. If this is not the case, consult Project Services.
To add a new resource to the project:
- Select the project from the list of projects.
- Click the settings gear icon in the header bar.
- Click the 'Add Person' button at the top of the 'Project Members' list.
- Select the resource from the appropriate dropdown in the popup window which appears (similar to below).
-
It is not necessary to set the rates. These are adopted from the Timesheet Category selected by resources when entering timesheets.
-
Select the following options and uncheck all others:
- Timesheet entry allowed?
- Timesheet approval required?
- Comments
-
Confirm that the appropriate Timesheet Category exists for the new resource in the 'Timesheet Categories' list. If the required category has not been setup, see Adding a new Timesheet Category to the Project.
Adding a new Timesheet Category to the Project#
Pre-Requisites
- Must be assigned as a Project Manager for the project in Avaza. If this is not the case, consult Project Services.
To add a new resource to the project:
- Select the project from the list of projects.
- Click the settings gear icon in the header bar.
- Click the 'Add Category' button at the top of the 'Timesheet Categories' list.
- Select the appropriate existing category from the dropdown. If an appropriate existing category does not exist, consult Project Services.